Scabbled the floor where the boiler will go, then painted. Unfortunately it appears that I really should have put down a thinned first coat. As the surface after scabbling was very coarse, the two-part water-based epoxy went on very thick; came in this morning to get the plumber started on the toilet and the paint was still wet - toilet completion deferred to Monday.
Floor prep. machines : 3-motor vacuum, scabbler, and grinder; second-hand toilet optional.
Friday, 22 January 2010